Table 5 Mission Rubber Company FCS Budget
FCS Budget Remaining
Services
FCS Budget
Technical Services
$14,300.00
$0.00
Material Testing Services
$13,200.00
$4,186.49
Total
$27,500.00
$4,186.49
Task 3.3 Technical and Testing Deliverables: Documents that are considered confidential to the production and results of the manufactured products will be marked “CONFIDENTIAL”.
FCS Project 4 - SafePath Products DK Enterprises coordinated with SafePath Products and its technical and material testing service providers to assist SafePath Products in the design and development of the Green Sidewalk Repair System that will be sold as a boxed surfacing kit to repair broken and lifted sidewalks. The rubber sidewalk repair system includes recycled tire granules, aggregate, a proprietary non- toxic fast set polymer binder; a 2.5” x 36” – 48” molded termination strip and an adhesive tube to adhere the strip to the substrate.
Task 3.4 Product Name: Green Sidewalk Repair System
Figure 4 Green Sidewalk Repair System
FCS Contractor Report – Confidential